Pennine Waterways News

Wednesday, 10 April 2019

Bosley Locks Closed

Bosley Locks have had to be closed to navigation after a void was discovered alongside Lock 3.

This was discovered in the course of operating the lock. There is a risk of the ground alongside the lock collapsing so the Canal and River Trust have closed the lock for investigations. They are looking at ways of allowing passage through the lock without endangering crews.

An update will be issued tomorrow.

With Marple Locks not due to re-open until 24th May, this means that the summit level of the Macclesfield and Peak Forest Canals is temporarily cut off.

Update 11th April:
CRT has issued the following statement -
"Our Teams have managed to erect a temporary platform which has been built above the void to enable the lock to still be in use.
"The flight is now open for navigation."

Update 16th April:
The flight will be closed on Wednesday 17th April between 8.00 am and 5.00 pm to allow repairs to be carried out on Lock 3.


Lock 3, Bosley flight, Macclesfield Canal

Saturday, 2 March 2019

Burnley Reopening Delayed

The closure of the Leeds and Liverpool Canal at Finsley Gate in Burnley is to be extended until May.

The Canal and River Trust has announced that the canal will not re-open in Burnley until Wednesday 8th May.

The Trust says that, once the canal was dewatered, it was discovered the amount of silt along the affected area was far greater than expected. The silt was tested and found to be contaminated, which means special measures have to be taken to remove it and dispose of it safely, causing significant delays to the project.

It was also found that the retaining wall was in a much worse condition than originally thought. This, too, has resulted in additional works.

CRT says that their contractors are doing everything they can to complete this project as soon as possible but will not be in a position to re-open the navigation until 8th May 2019. The Trust sincerely apologises for the inconvenience this may cause.

The stoppage at Finsley Gate was to enable canal relining works, work to the towpath retaining wall and offside soft bank protection.

Finsley Gate on the Leeds and Liverpool Canal at Burnley.

Wednesday, 6 February 2019

Marple Locks Reopening Delayed

Another setback has been announced for boaters wishing to use the Peak Forest Canal.
Trouble-hit Marple Locks are now to remain closed until the end of May.

The Canal and River Trust has revealed that rebuilding work at Lock 11 in Marple is a few weeks behind schedule. It is now planned to re-open the canal to boats at the end of Friday 24th May 2019.

It had originally been planned to re-open the locks in mid-March,. Engineers say they encountered delays in the piling phase of the works, with ground drilling and the installation of reinforced concrete piles behind the existing lock walls proving slower than expected. Some design changes were also needed due to site constraints. The piling is now complete and the ground stable so that the failed lock walls can now be carefully dismantled.

The re-building of the lock walls back to the correct alignment is complex and time consuming, as construction has to comply with heritage requirements, with Lock 11 being a Grade II Listed structure.

Lock 11 has been closed since July 2018 because the sides were moving slowly inward. It had been open on a restricted basis for only a few weeks after the lock flight had been closed from September 2017 because of serious subsidence at Lock 15.

These extended stoppages have affected boaters intending to navigate the Cheshire Ring.