Temporary dams and pumps are being installed to create a dry working environment. The previous temporary repair will be removed and the failed section of culvert will be uncovered.
A permanent concrete repair will be carried out to the culvert over the next week and then new puddle clay will be laid over the top to ensure a watertight seal. The contractors will then remove the temporary dams and pumps, refill the canal, reinstate the towpath, site compound area and rebuild the boundary wall.
Currently the work is expected to be completed and the canal re-opened by 24th January, however this is dependent on good weather and working conditions over the next few weeks. Updated information will appear on this page.
The Rochdale Canal below Lock 7 in Mytholmroyd